Summary
The Woolwell Centre – A vibrant community hub focused on connection and enrichment. The centre has ‘sky rocketing utility bills’ and wanted to modernise the building.
Installation
Tiger Neo N-type 60HL4-(V) 460-480 Watt
56.640kW of Solar Power
118 x JKM480N-60HL4-V
480 Watt panels
25 Year Product Warranty & 30 Year Linear Performance Warranty
51,373kWh per year
SolaX Power
50 kW Total Inverter Rating
2 x X3H-ULTRA-25K
Outcomes
- £6,787 estimated first year savings
- 6 years, 7 months payback
- 126% energy from solar
- £184,351 lifetime bill savings
- 13 tonnes avoided CO₂ per year
- 278 long haul flights avoided
- 2,500 trees planted
- 388,883 Car KM avoided
Bloom always appeared to be the lead in responding to any queries and always gave us a good solution to our needs. Bloom came out on top!
Love Barn
Location Dartington Install Date Feb 2024Summary A high consumption rented property required a solution to offset high summer usage. We designed a fully optimised system utilising multiple roof faces, providing backup functionality and battery storage. Installation 21...
Marian Rudd
Location Totnes Install Date Apr 2024Summary A passivhaus in the centre of Totnes needing solar to offset electricity usage. We designed a flat roof system combined with battery storage an EV charger and a hot water diverter. The system was also fully optimised and...
Mark Carter
Location South Brent Install Date May 2024Summary A family house near Dartmoor prone to power cuts, probably mainly due to the over ground power cables. The roof of the house and the shed provided ample space for solar panels and battery storage as well as electric...